VARANASI: The district administration published a draft assessment on Tuesday, November 17, 2026, for acquiring 1.9918 hectares of private land to widen and strengthen roads serving the proposed Sant Kabir Textile and Apparel Park. The study covers Ramna, Seergovardhanpur and Naipura Kalan in Sadar tehsil, and identifies about 165 families whose holdings would be partly affected.

The immediate issue for residents is the road corridor and the assets recorded within it. Landowners in the three villages should compare their village, plot and structure details with the draft's annexures. The document concerns two lane and four lane access roads; its acquisition area is separate from the land identified for the textile park itself.

The Public Works Department's Construction Division I is the proposing office named for the road works. The study says the improved approach would connect the park with the national highway near Dafi toll plaza. Residents seeking the detailed road design should ask that division for the applicable plan rather than infer a final alignment from a general description of the park.

How the proposed land is divided

The district's draft report notice carries November 17 as its start date. The linked assessment sets out 1.0714 hectares in Ramna, 0.7644 hectares in Seergovardhanpur and 0.1560 hectares in Naipura Kalan. Together these make the stated 1.9918 hectares.

The assessment classifies the proposed acquisition as private agricultural land and describes the selected pieces as adjoining. Its land schedules and asset inventories are therefore the relevant starting point for someone checking whether a particular holding falls within the proposal. The village totals alone cannot show which part of an individual plot would be needed.

  • Ramna: 1.0714 hectares.
  • Seergovardhanpur: 0.7644 hectares.
  • Naipura Kalan: 0.1560 hectares.
  • Total proposed private acquisition: 1.9918 hectares.
  • Families identified by the draft: approximately 165.

According to the study, the families said the land proposed for acquisition formed only part of their holdings, and the assessment concludes that none would become landless as a result. It nevertheless records structures, including houses, boundary walls and tube wells, on some of the identified plots. Retaining other land does not mean there is no asset loss on the portion being acquired.

The report was prepared for the Special Land Acquisition Officer, whose address on the cover is Sanskritik Sankul, Maqbool Alam Road, Chaukaghat. Residents checking the household record should distinguish questions about ownership and valuation from questions about the engineering design, for which the report points to the Public Works Department office.

What the access roads are intended to serve

The study describes the proposed textile and apparel park at Ramna as occupying 75 acres. It says land previously recorded with the city's waterworks department was transferred to the Handloom and Textile Industry Department for the park. That larger park site and the much smaller acquisition studied for access roads should be kept separate when assessing the proposal's local footprint.

The park is described as a public private partnership intended to support the Banarasi weaving and sari industry. Its proposed facilities include weaving, cutting, dyeing, printing, apparel production and processing areas, alongside storage, testing, exhibition and design facilities. These are features described in the draft, rather than a declaration that all units are operational.

For smaller weavers, the proposed facilities include industrial sheds designed for units to begin using prepared infrastructure. The document also describes an effluent treatment system based on zero liquid discharge. That is the intended treatment arrangement in the project description; the assessment is not an operational pollution performance report.

On construction, the report anticipates demand for materials such as earth, bricks and stone aggregate, sourced locally and from outside the area. It says contractors could employ local unskilled and semi skilled workers alongside other staff. This describes a possible construction benefit, without constituting a recruitment advertisement, a wage commitment or an application process for residents.

What residents should do

Read the complete road assessment and annexures with the household's land records available. Check structures as well as land area, and keep a written note of any mismatch to raise with the responsible office. The report says detailed design information is available with the executive engineer of Construction Division I.

The listing remains dated through December 31 on the district website. Its accompanying notice does not label that date as an objection deadline or announce when a particular household must hand over land. Families should use the separately issued notice applicable to their plot for any procedural date.

Related local background includes the Harsos road assessment, the earlier textile manufacturing project and the sari producers' trade fair listing. Those reports concern separate developments; this new document addresses the park's approach roads in three Sadar villages.