VARANASI: A draft land impact report published by the district administration on Tuesday, November 17, 2026, identifies 22 landowning families in Kallipur and Gaur Madhukar Shahpur whose property is proposed for acquisition for the Anand Kashi urban expansion scheme. Eleven families told the study team that acquisition of their identified private land would leave them landless and require relocation, bringing household impacts into focus alongside the township plan.
The two villages are in Rajatalab tehsil. The draft covers 9.6860 hectares of private land, comprising 8.0087 hectares in Kallipur and 1.6773 hectares in Gaur Madhukar Shahpur. Residents whose holdings are identified can compare the plot and household schedules with their records and check whether buildings, wells and other assets have been recorded correctly.
The document is a draft Social Impact Assessment, with a proposed management plan for the effects of acquisition. It says public hearings will follow the draft stage and a final report will be submitted after those hearings. The district listing does not give a hearing date or time, so residents need the subsequent official notice before making arrangements to attend.
Which households and assets the study covers
The district administration's publication page links the report and gives November 17 as its start date. The household table identifies 18 affected families, containing 123 people, in Kallipur. The corresponding figures for Gaur Madhukar Shahpur are four families and 30 people. The assessed population across the two villages is therefore 153.
The land figure concerns the private area proposed for acquisition in this assessment. It should be read with the report's village and plot schedules rather than used as the size of every part of Anand Kashi. The document explains that the wider scheme has involved land pooling and direct purchase, while some holdings have not transferred to the development authority.
The draft records residential houses, sheds, boundary walls, wells, tubewells and handpumps on the proposed acquisition plots. A separate asset schedule is included in Appendix 4. These details matter to households because the assessment concerns property attached to the land as well as the land itself.
It also records concerns about valuation. Some owners of highway-side plots told the assessment team that their better location warranted higher compensation than plots inside the village. Those concerns are recorded in the study; they are not a newly announced compensation rate or a settlement reached with those owners.
What the project proposes
The report describes Anand Kashi as a planned township near the Ring Road and the Prayagraj to Varanasi highway. Its stated purpose is to create development outside the crowded historic centre and provide planned residential and institutional space. The assessment presents those benefits as the project's objectives, rather than reporting them as completed improvements.
Proposed uses include residential plots of different sizes, commercial plots and group housing areas. The planned facilities include internal roads, green areas, a central eco park, a Miyawaki forest and space for meditation and yoga. Health centres and schools are also envisaged, together with underground electricity cabling, drainage, water supply and sewerage infrastructure.
Alongside the projected benefits, the study discusses loss of agricultural land and effects on livelihoods. It notes that dependence on land can extend beyond its owner to labourers, producers, sellers and others connected with farming and livestock. That is why its household and livelihood findings are relevant to people who do not expect to receive a housing plot themselves.
What residents should do
Read the village-wise schedule and the relevant plot entries in the official draft report. Appendix 1 lists affected households by plot, while Appendix 4 records assets. Keep the distinction between a recorded concern, a proposed mitigation measure and a final decision clear when checking the entry for a particular holding.
The report is addressed to the Special Land Acquisition Officer at Sanskritik Sankul Bhawan on Maqbool Alam Road, Chowkaghat. Residents seeking clarification about the assessment can use that issuing-office information and the Varanasi Development Authority's official website. No new application charge, plot booking deadline or compensation payment schedule is announced on the district publication page.
What happens next
The draft describes consultations and fieldwork undertaken in October 2026. November 17 is the publication date of this document, not the date when the household interviews took place. The district page lists December 31 as its end date; it does not identify that date as a public hearing or an objection deadline.
Other local land matters remain separate: earlier reporting covered the Tengra terminal rail link assessment, the Garhwa layout warning and the logistics park concession. Their dates and procedures do not replace the hearing arrangements still to be announced for this draft.