GURUGRAM: The housing regulator's public file recorded the upload of Elevate Vista's registration certificate on Friday, November 27, 2026, giving people examining the Sector 63A project a certificate that runs until September 30, 2034. The document is dated November 5 and covers the first phase of the group housing development. Its completion date differs from the December 31, 2034 date entered in the promoter's public application.
The distinction matters for prospective buyers comparing documents for the project. Haryana Real Estate Regulatory Authority's project register marks the application approved and the certificate uploaded, with no next hearing required. Elevate Edition Realtech Private Limited is identified as the promoter, with its registered and corporate address at One Horizon Centre on Golf Course Road in Sector 43.
The certificate and application carry different dates
The official project register identifies the application as RERA-GRG-2308-2026. It records receipt and online submission on October 7. The registration number is GGM/1097/829/2026/69, dated November 5. November 27 is the portal's certificate upload date, rather than the date on which the certificate says registration began.
According to the registration certificate, validity starts on November 5, 2026 and ends on September 30, 2034, unless the authority extends it under the applicable legislation and rules. The certificate describes that endpoint as the completion date declared for this phase. It also says the registration rests on information supplied by the promoter and the authenticated detailed project information accompanying the certificate.
The public application, by comparison, lists January 1, 2027 as the likely construction start and December 31, 2034 as the likely completion date. Those entries describe the promoter's submitted programme. Readers should keep the application timetable and the subsequently issued certificate's validity period separate when examining the record.
- Location: Sector 63A, Gurugram.
- Certificate upload shown on the portal: November 27, 2026.
- Certificate date and start of registration: November 5, 2026.
- Registered phase: 7.825 acres.
- Certificate endpoint: September 30, 2034.
What the registered phase contains
The certificate places the development within a total licensed area of 10.525 acres. It says the planning department approved development in two phases, while this registration covers Phase I. The smaller registered area should therefore be used when comparing the first phase with the overall licensed development.
For Phase I, the certificate lists four residential towers, A, B, C and D, together with an economically weaker section component. Its unit schedule records 380 residential homes, 68 EWS units and eight commercial units. The stated floor area ratio area is 86,544.186 square metres. These figures describe the registered scheme and do not establish that construction or occupation has taken place.
The planning licence identified in the certificate is number 43 of 2026, dated March 10, with validity until March 9, 2031. That licence period is another date range in the file, separate from the regulator's registration period. The application also records building plan approval on October 6, 2026.
Approval requirements remain part of the record
The November 2 hearing entry records the promoter's undertaking to obtain environment clearance, fire scheme approval, and approval of service plans and estimates within six months of registration. The certificate confirms that three demand drafts of Rs 25 lakh each were submitted on November 3 as security for timely submission of those approvals. Together, those instruments amount to Rs 75 lakh.
The same hearing record requires tree cutting permission within six months and mining permission before construction starts. It states that failure to submit the specified approvals within the stipulated periods would lead to forfeiture of the security and could attract further regulatory action. These are the requirements recorded at that hearing; the entry does not establish the subsequent completion status of each approval.
The promoter's application separately identifies GMDA for water supply, sewage disposal and stormwater drainage connections, and DHBVN for electricity. Its internal infrastructure estimates include Rs 271.27 lakh for water supply, Rs 68.82 lakh for stormwater drainage and Rs 426.84 lakh for rainwater harvesting. These are proposed project expenditure figures declared in the application, rather than audited expenditure or municipal spending approvals.
The certificate also requires the promoter to put 70 percent of project receipts into a separate scheduled bank account for land and construction costs. At booking and allotment, it must make the sanctioned plans, specifications and stage wise completion schedule available, including the programme for water, sanitation and electricity. These obligations give buyers specific documents to compare with the project details supplied to them.
For readers following other local regulatory files, earlier coverage explains the approval conditions for a project in Sectors 81 and 86, the objection window for a separate phase application, and an individual delay interest order in Sector 106. Each concerns a separate project or proceeding; their terms should not be applied to Elevate Vista.