GURUGRAM: The Haryana Real Estate Regulatory Authority issued a public notice on Tuesday, November 17, 2026, inviting objections to the registration application for Experion Emerelle in Sector 88A. The application covers 0.72303 acres identified as Phase 2. Residents and other concerned people can inspect the documents and submit objections until December 4, ahead of a hearing on December 7.

The applicant is Experion Developers Private Limited. The notice places this application within a larger licensed site measuring 7.81875 acres, developed under the mixed land use provisions of the transit oriented development policy. The distinction between the overall site and the smaller area now before the regulator matters: the November notice concerns Phase 2, rather than a fresh application for the entire licensed parcel.

What the November 17 notice covers

According to the official public notice, the promoter submitted the Phase 2 registration application on November 13 under Section 4 of the Real Estate (Regulation and Development) Act, 2016. The authority is making that application available for scrutiny. The notice does not itself announce that a registration certificate has been granted.

The land falls under DTCP licence 135 of 2024, dated November 4, 2024. The notice records a revised demarcation and zoning plan approved on December 11, 2025, followed by a revised phasing plan approved on September 30, 2026. It describes the approved arrangement as Phase I, Phase II and a component labelled No Phase.

Building plan approval for the Phase 2 mixed land use group housing component is dated November 12, 2026. The notice identifies the approval as memo ZP-2181-Loose/SD(RD)/2026/39788. That document reference gives anyone examining the file a way to distinguish the relevant building plans from earlier approvals for other parts of the site.

The authority also cites Section 14(2)(ii), under which alterations or additions to a sanctioned project plan require written consent from at least two thirds of the allottees. Alongside that provision, it records the promoter's affidavit stating that it had created no advertising, marketing, bookings, sales or third party rights in the project named Experion Emerelle up to that point. This is the promoter's declaration recorded in the notice.

Inspection and hearing arrangements

The application and related documents can be seen at the authority's office on working days until December 4, 2026, between 11 am and 4 pm IST. Objections must also be filed by December 4. Anyone wishing to appear may attend the hearing scheduled for December 7 at 11 am IST. The hearing date falls after the inspection and objection deadline, so it should not be treated as an extension of the filing window.

  • Project under the new notice: Experion Emerelle, Phase 2, Sector 88A.
  • Application area: 0.72303 acres.
  • Applicant: Experion Developers Private Limited.
  • Last inspection and objection date: December 4, 2026.
  • Hearing: December 7, 2026, at 11 am IST.

The authority's public Gurugram portal gives its address as the New PWD Rest House, Civil Lines, Gurugram. Readers preparing a representation should match the project name, phase and application date against the notice, particularly because a similarly named application exists for another part of the same licensed land.

How the earlier phase differs

An earlier notice dated October 13 concerned Experion Emerelle Reserve, covering Phase 1 and the EWS block over 7.095715 acres. Its application was dated October 5. That earlier notice used the same licence number and total licensed area, but related to a different registration area and an earlier hearing timetable.

The Reserve application record identifies its location as village Harsaru, Sector 88A, and records proceedings held on November 2. Those proceedings approved the proposal subject to rectification of deficiencies and conditions for issuing the certificate. The record should be read as background to the larger development, without transferring that decision to the Phase 2 application now open for objections.

The November 2 Reserve proceedings required three separate security deposits of Rs 25 lakh each for environmental clearance, fire scheme approval, and service plans and estimates. They also specified separate time limits for those approvals and for updated airport height clearance and road access permission. These were conditions in the Reserve record, rather than a list of conditions imposed through the new Phase 2 notice.

The new public notice does not supply apartment prices, a possession commitment or a count of homes for Phase 2. Its immediate local significance is the opportunity to examine the filed plans before the regulator considers registration. Separate local regulatory coverage includes the Marbella North notice, the SS Camasa objection process and the revised November 19 hearing list. Each concerns a separate proceeding with its own dates.