GURUGRAM: A housing regulator order listed as uploaded on Thursday, November 26, 2026, awards a buyer in Godrej Meridien Phase 1 in Sector 106 annual delay interest of 10.95% and requires the developer to revise the buyer's account before collecting any remaining dues. The Haryana Real Estate Regulatory Authority, Gurugram, decided the complaint on November 17. Its newly published judgment gives a sequence for adjusting the interest, settling the account and completing possession and conveyance.

The case concerns Godrej Real View Developers Private Limited and a second floor apartment in Tower 1 at the group housing project. Chairman Arun Kumar's order addresses the individual complaint, numbered 2413 of 2025. Residents checking their own paperwork should distinguish its directions from a project wide award: the operative relief is for the complainant in this case.

How the possession deadline was assessed

The agreement for sale was executed on August 31, 2018. Its possession clause gave September 30, 2022 as the deadline for units in Phase 1. The authority allowed six additional months under its pandemic extension and used March 30, 2023 as the due date for this buyer's possession claim.

In its findings, the authority recorded that the occupation certificate had been obtained on March 31, 2023, while the possession intimation to the buyer was dated May 1, 2025. It held the intervening delay attributable to the promoter. This distinction matters because the existence of an occupation certificate and communication of an offer to an individual allottee were separate dates in the dispute.

The developer contested liability and cited pandemic disruption, shortages of labour and materials, and restrictions on construction. It also argued that the buyer had not completed payment obligations after the possession letter. The authority considered those submissions, noted that the six month pandemic extension had already been allowed, and found a failure to provide possession by the adjusted deadline.

The full official judgment records Rs 1,78,43,583 as the sale consideration in its project particulars and Rs 1,61,05,999.84 as the amount paid. It does not state a single final rupee total for the interest award. Instead, it directs an account adjustment using the prescribed rate and period.

Interest and account adjustment come first

The operative directions award interest on the paid amount for every month of delay from March 30, 2023 until the offer of possession plus two months, or actual handover, whichever is earlier. The order therefore defines an endpoint for calculation. It does not award an open ended payment running automatically until the date a reader sees this report.

The two month allowance reflects the authority's finding that the buyer learnt of the occupation certificate through the possession offer. The judgment explains that practical arrangements and inspection of a finished apartment take time, while linking that allowance to a unit being habitable when handed over.

  • The promoter must issue a revised account after adjusting delay charges within 30 days.
  • The buyer must pay any outstanding dues within 60 days of receiving that revised account.
  • Possession and the conveyance deed must be completed within three months of the order, with applicable stamp duty and registration charges paid.
  • The judgment gives the promoter 90 days to comply with its directions.

The separate periods have different triggers. In particular, the buyer's 60 day payment period begins on receipt of the revised account. November 26 is the upload date shown in the official judgment register, while November 17 is the decision date printed in the order. No upload time is stated in that register.

Other relief and the next documents to check

The authority directed the promoter not to charge amounts outside the August 31, 2018 buyer's agreement. It also required the same prescribed 10.95% rate for interest charged to the allottee in case of default. The judgment attributes its rate calculation to the lending benchmark it considered on the decision date; this report is describing the rate ordered in this case.

A separate request to remove allegedly one sided contractual clauses was not entertained. The authority reasoned that the buyer had signed the agreement voluntarily and raised that challenge later. On the request for a benefit relating to GST input tax credit, it left the allottee free to approach the State Screening Committee Haryana. It did not calculate or award a tax credit amount.

The immediate documents arising from the decision are the revised account, its adjustment for delay interest, and the possession and conveyance records. For background on other local regulatory matters, read the earlier reports on allottee status in a Sector 104 complaint, delay in filing housing appeals and public scrutiny of a separate registration application.