GURUGRAM: The Haryana Real Estate Appellate Tribunal dismissed 19 connected allottee appeals against Silverglades Infrastructure Private Limited on Saturday, November 21, 2026, after rejecting the explanation for delayed filing in the lead case. The common order concerns appeals from proceedings before the Gurugram real estate authority and turns on whether the applicants had pursued their remedy diligently.

The parties listed in the order include residents of South City I, Sector 67, Shivpuri and Ardee City in Sector 52, alongside appellants living outside Gurugram. Those are the addresses of parties in the case. The tribunal's order does not identify the housing project's sector, and those residential addresses should not be read as its location.

Why the appeals were dismissed

The bench comprised chairman Justice Rajan Gupta and judicial member Dr Virender Parshad. It said common questions of fact and law arose in the connected matters and used Appeal 184 of 2023, brought by Sat Pal Dewan, to set out the facts. The authority's official judgment register records both the decision and its upload on November 21. No publication time is displayed.

In the lead matter, the challenged authority order was dated September 28, 2021. The appellant said it had been uploaded on December 20, 2021. His appeal was accompanied by applications seeking permission to excuse a delay of 439 days in filing and a further 77 days in refiling. These are the lead case's procedural figures, rather than a separate calculation for every appellant.

The explanation referred to meetings between the appellant and counsel to obtain legal advice, time taken to supply documents, and the examination and verification of the record before the appeal was filed. The appellant maintained that the delay had occurred for bona fide reasons beyond his control. The tribunal heard the parties but found those grounds unconvincing.

The bench also considered the sequence in which the two sides had approached it. Its order says the promoter had appealed in 2022, while the allottee waited before bringing his own challenge. It regarded the allottee's appeal as an afterthought following the promoter's appeal and found that reasonable diligence had not been demonstrated.

The 60 day appeal provision

Section 44(2) of the Real Estate (Regulation and Development) Act provides a 60 day period for an appeal. The Act published on the authority's website measures that period from receipt of a copy of the direction, order or decision. It also permits the tribunal to entertain a later appeal when satisfied that sufficient cause prevented filing within that period.

The November 21 bench applied that distinction: the law allows consideration of a late appeal, but the applicant must establish an adequate explanation. In this case it found no convincing reason to excuse the stated 439 day delay. The application was dismissed and the appeal consequently failed. Pending applications were also disposed of.

The judgment cited a Supreme Court decision delivered on February 9, 2026, concerning the public policy underlying limitation periods. The tribunal referred to the need for legal remedies to reach an end rather than leave disputes pending indefinitely. Its decision in the connected Silverglades matters rests on the filing explanation and diligence assessment recorded in the common order.

What the earlier authority order contained

The 11 page common order reproduces the operative directions from the lead case's September 2021 ruling. That earlier ruling required the promoter to pay delayed possession interest at 9.30% a year, calculated from May 30, 2017, to April 20, 2020. The end date incorporated two months after the February 20, 2020, possession offer.

The earlier directions required payment of the interest arrears within 90 days of that order. They also required the allottee to clear outstanding dues after adjusting delayed possession interest and take possession within the period specified there. The quoted ruling applied the same prescribed interest rate to allottee defaults and barred holding charges. These are directions reproduced from 2021, rather than fresh payment deadlines starting this November.

The tribunal directed that its new order be sent to the parties or their counsel and the authority, with the file consigned to the record. It did not set out a new project completion date or announce that any money had been recovered. Readers following other housing proceedings can consult the separate reports on the Ashiana Anmol refund appeal, the Ashiana Mulberry appeal deposit and the Emerald Hills compensation order.