GURUGRAM: A housing regulator judgment uploaded on Friday, November 27, 2026, directs Vikas Park Private Limited to pay delay interest in three complaints concerning Hero Homes in Sector 104, while adjusting compensation already paid to the buyers. The Haryana Real Estate Regulatory Authority, Gurugram, decided the matters on November 17. Its published order gives the developer 90 days to comply.
The development concerns apartments at the group housing project in Dhanwapur village. Chairman Arun Kumar dealt with complaints 3565, 4475 and 4793 of 2025 through one common decision, using the first complaint as the lead case. The publication brings the detailed findings into the public judgment register; November 27 is the upload date, rather than the date on which the authority heard or decided the dispute.
One decision for three apartment complaints
The authority recorded that the complaints raised similar questions about delayed possession in the same project. It considered the developer's obligations under the buyers' agreements and the real estate law, then directed that the decision apply to the other two listed complaints with the necessary changes for their individual facts. This makes the common order relevant to the three identified proceedings.
The lead complaint concerns a 1,099 square foot apartment in Tower T03, with an agreement dated April 22, 2019. The second concerns a 1,389 square foot apartment in Tower T02, with an agreement dated May 18, 2019. The third concerns a 1,689 square foot apartment in Tower T04, with an agreement dated May 8, 2019. The areas are the super areas recorded in the judgment's case table.
That table lists sale consideration of Rs 77,53,105 for the first case, Rs 92,98,655 for the second and Rs 1,05,71,800 for the third. These are the contractual consideration figures in the proceedings. The operative direction calculates interest against the amounts paid, so the consideration column alone does not supply the final interest payable to each buyer.
- Project: Hero Homes, Sector 104, Dhanwapur, Gurugram.
- Complaints: 3565, 4475 and 4793 of 2025.
- Decision: November 17, 2026; upload: November 27, 2026.
- Interest ordered: 10.95% a year, with adjustment for compensation already paid.
How the authority fixed the delay period
The agreement's possession date was August 31, 2023. The authority allowed a six month extension on account of the pandemic and used February 28, 2024 as the due date. The case table records the same adjusted deadline for all three complaints. It also records an occupation certificate dated January 20, 2025 and possession offers dated February 25, 2025.
In its findings, the authority distinguished the certificate from the later communication to the buyer. It concluded that the lead complainant learnt of the occupation certificate through the possession offer. It therefore allowed two months from that offer for practical arrangements, including documents and inspection of the finished apartment, subject to the unit being habitable when possession was taken.
The interest period runs from February 28, 2024 until the possession offer plus two months, or actual handover, whichever occurred earlier. That endpoint matters when checking a calculation: the order defines the period through the buyer's possession records. The judgment also lists conveyance deeds dated June 5, June 2 and June 27, 2025 for the three cases respectively.
The developer contested liability. Its reply said it applied for the occupation certificate on February 21, 2024, and argued that completion had been held up by approval paperwork. It also relied on the subsequent conveyance deed and disputed the buyer's continuing claim. The authority nevertheless found a failure to offer possession by the adjusted contractual deadline and awarded the statutory delay interest.
The project particulars record registration 24 of 2018, dated November 13, 2018, and a continuation certificate dated March 27, 2025 with validity until February 28, 2027. Those registration entries form part of the project history in the judgment. The present ruling determines the buyers' delay claims under their agreements.
Earlier compensation must be adjusted
The authority's lead case findings record Rs 2,58,479 already paid as delay compensation and require its adjustment. The final directions extend the adjustment principle to compensation previously paid in the covered complaints. An individual calculation therefore needs both the interest due under the order and the record of compensation already received.
The judgment sets the annual rate at 10.95%, using the lending benchmark considered on November 17. It gives the respondent 90 days to carry out the directions and states that failure would bring legal consequences. It does not provide a single combined rupee award for all three complaints. The full official common judgment should be read alongside the authority's upload register.
For separate Gurugram proceedings, earlier reports cover the Hero bike price list: HF Deluxe from Rs 59,477, Splendor+ Rs 78,912, Xtreme 160R Rs 1,13,829, the Gurugram Sector 106 order sets 10.95% delay interest and the Gurugram Sector 10 Civil Hospital opens AMRIT pharmacy. Those decisions concern their own records and relief. The newly uploaded Hero Homes judgment disposes of the three Sector 104 complaints identified in its opening table.