GURUGRAM: A proposed flyover and underpass at Ardee City Chowk, where Sectors 43, 44, 52 and 52A meet, were detailed in reports published on Wednesday, November 18, 2026, with GMDA officials putting the estimated cost at Rs 225 crore. The authority has prepared the detailed project report for a junction used by commuters travelling between Golf Course Road and the Gurugram to Sohna corridor.
The proposed elevated route would start near Paras Hospital, pass over Ardee City Chowk and the Kanhai traffic signal, and join the main road dividing Sectors 51 and 52. Officials described a single pillar design intended to carry through traffic past successive signals, rather than return it to a queue immediately after the flyover.
How the junction plan would change journeys
GMDA executive engineer Amit Godara said the flyover alignment would bypass the signals near Paras Hospital and Kanhai Chowk. His explanation identifies the traffic movements the authority wants to separate from surface traffic. The underpass is the other component of the proposed junction treatment, allowing the two intersecting roads to be handled at different levels.
The two opened reports agree that both a flyover and an underpass are proposed and attribute the approximately Rs 225 crore estimate to Godara. They describe three lane structures. The expenditure figure remains an estimate attached to the proposal; it should not be read as the value of an awarded construction contract.
Ardee City Chowk carries journeys from IFFCO Chowk on the Delhi to Jaipur highway towards Golf Course Extension Road, as well as movement between Golf Course Road and the Sohna road. Around 100,000 vehicles use the junction daily, according to the reported planning assessment. The intersection therefore serves traffic crossing between major corridors alongside residents entering neighbouring sectors.
The reported signal cycle is about 90 seconds. During busy periods, motorists can have to wait through two or three cycles before crossing. That repeated wait is the congestion problem cited in the current reports. The project description does not provide a measured reduction in journey time once the structures open.
Another difficulty concerns traffic approaching from Sector 45 towards Golf Course Road. Motorists currently take a detour towards Millennium City Centre and make a U-turn before returning to the junction. Officials said the proposed arrangement is intended to remove that detour and improve movement on the two main roads passing through the intersection.
Design is ready, implementation details remain to come
The November 18 accounts describe a prepared design and detailed project report. They do not establish that a contractor has been appointed or that excavation has begun. A construction start date, an opening date and a final traffic diversion map for Ardee City Chowk were not supplied in the material reviewed.
For residents of the adjoining sectors, that distinction has an immediate practical consequence: the proposal cannot be used as an instruction to change routes or as evidence that an existing signal has been removed. Any construction restriction would need its own notice identifying the affected road, permitted access and applicable dates.
- Location: Ardee City Chowk, adjoining Sectors 43, 44, 52 and 52A.
- Proposed works: a flyover and an underpass.
- Reported estimate: approximately Rs 225 crore.
- Flyover landmarks: Paras Hospital, Ardee City Chowk, Kanhai signal and the Sector 51 and 52 dividing road.
- Current stage described: detailed project report prepared.
Nearby road schemes provide context
The proposal sits near other junction improvements already covered on dalimss.news. The earlier report on three approved flyover and underpass projects describes separate works at Dadi Sati Chowk, Ambedkar Chowk and Millennium City Centre. Those approvals concern their named junctions and should not be taken as approval of the Ardee City estimate.
Our report on the Vyapar Kendra and Galleria circulation decision explains how future Millennium City Centre underpass construction is expected to require a separate traffic plan. It is useful background for residents following several nearby schemes whose implementation stages differ.
Further south, the Subhash Chowk to Hero Honda Chowk service road tender concerns another corridor. Its procurement timetable does not set the timetable for Ardee City. Keeping the location and stage of each project separate helps commuters interpret subsequent notices accurately.
GMDA also lists WhatsApp number 7840001817 and missed call number 9873353224 for public contact. Residents seeking clarification about the proposed route can name Ardee City Chowk and the nearby landmarks so that a query is distinguished from works at other intersections.