Varanasi Waste Hits About 1,100 Tonnes a Day; Nagpal Orders Karsada Capacity Lift

Municipal Commissioner Himanshu Nagpal inspected the Karsada solid-waste processing plant on Sunday, 13 September 2026, and ordered a capacity lift after city waste rose to about 1,100 tonnes a day from a previous band of roughly 600–700 tonnes. Additional Municipal Commissioner Durgesh Mishra and Assistant Municipal Commissioner Indra Vijay were present. The copy is a civic capacity story — plant orders on the ground — not a political attack.
Nagpal’s on-record directions covered the processing line and the site logistics around it. He ordered additional trommels. RDF-line equipment has arrived and is to be installed and commissioned as soon as possible. A proposal is to make the Leachate Treatment Plant fully functional. Compost storage is to get a concrete floor and a shed. Accumulated waste along the west stem road is to be cleared so garbage vehicles can move and the road can be widened.
Routine laboratory tests of compost were underlined. A monthly drone survey of the plant was ordered. Local office upkeep at the site was flagged. Those are housekeeping and monitoring stamps that sit beside the hardware orders. Together they sketch a commissioner visit that treated Karsada as a working plant under pressure, not a ribbon-cutting stop.
The jump from about 600–700 tonnes a day to about 1,100 is the load figure Nagpal used. This desk does not import older Miyawaki or legacy-dump masterplan numbers into this piece. The locked arithmetic for Sunday is the commissioner’s current daily-waste stamp and the capacity orders that followed from it. Extra trommels and an RDF line ready to commission are how the plant is being told to absorb the higher intake.
Leachate treatment going fully functional is a liquid-side order alongside the solid-side trommel and RDF push. Compost that sits on bare ground without a shed is harder to keep to spec; a concrete floor and covered storage are meant to tighten that end of the chain. Lab tests on a routine cycle are the quality check Nagpal named. Drone surveys once a month add an overhead view of how stockpiles and vehicle paths actually look between inspections.
The west stem road matters because garbage trucks are the plant’s bloodstream. Waste piled along that approach slows the fleet and blocks any widening. Clearing it is both a traffic fix and a throughput fix. Without truck movement, trommel capacity on paper does not turn into processed tonnes on the ground.
Varanasi Municipal Corporation’s solid-waste file often splits between collection politics and plant engineering. Sunday’s inspection stayed on the engineering and site-ops side: trommels, RDF, leachate, compost shed, road clearance, lab tests, drones, office upkeep. Readers looking for a wider sanitation manifesto will not find one here. Readers looking for what the commissioner ordered at Karsada on 13 September will.
Until later progress notes revise the plant’s working capacity, the locked civic stamp is about 1,100 tonnes a day of city waste, a Sunday inspection by Nagpal with Mishra and Indra Vijay present, and a set of hardware and housekeeping orders aimed at matching Karsada’s processing line to that load.
Sources and reporting
Municipal Commissioner Himanshu Nagpal site inspection Sunday 13 Sep 2026, Karsada solid-waste processing plant; city waste previously ~600–700 tonnes/day now ~1,100; additional trommels; RDF line equipment has arrived, install and commission ASAP; proposal to make Leachate Treatment Plant fully functional; concrete floor and shed for compost storage; clear accumulated waste along west stem road so garbage vehicles can move and road can be widened; routine lab tests of compost; monthly drone survey of plant; local office upkeep; Additional MC Durgesh Mishra and Assistant MC Indra Vijay present.
Related Stories

Thieves Hit Two Shops in One Night at Bareka’s Gumti Market

Kotwali Police Arrest Siddharth Sahni Within a Day of a Scooty Theft

Manduadih Police Arrest Raju Rajbhar After Paan-Shop Theft Opposite a Picket

Kashi Vishwanath CEO Vishwa Bhushan Mishra Transferred to UPSSSC as Deputy Secretary

Kashika Colours-and-Ragas Festival Opens at Town Hall With Nirala Staging and Mishra Recital