VARANASI: The National Highways Authority of India received 32 bids across four construction packages for the proposed Ganga and Varuna elevated corridors, the Ministry of Road Transport and Highways announced on Friday, November 27, 2026. The new bidding update concerns about 89.2 km of planned connections serving places including Ramnagar, Kashi railway station and the Varanasi Ring Road.
For residents and commuters, the development is a procurement milestone for projects approved in July. The ministry's November 27 release, issued at 6:02 pm IST, reports bidder participation and sets out the planned routes and projected journey savings. It does not name successful contractors or announce that either corridor has opened.
People planning trips to BHU, Namo Ghat, Ramnagar Fort or the railway stations should continue to check existing route and traffic notices. The bidding announcement contains no new public diversion schedule, construction start date or opening date. Its travel time figures describe the ministry's expectations for the completed projects.
How the four packages attracted 32 bids
The official November 27 ministry release gives the Varuna corridor eight bids for its first package and seven for its second. The Ganga corridor attracted eight bids for its first package and nine for its second. The package counts add up to 32 submissions; they should not be read as a statement that 32 different companies participated.
Both corridors are to be implemented through the Hybrid Annuity Model. The ministry lists total capital costs of Rs 10,998.32 crore for the Varuna project and Rs 14,447.64 crore for the Ganga project. Together those stated costs total Rs 25,445.96 crore. The release does not identify a winning financial offer for any package.
The 43.2 km Varuna corridor will connect NH 31 with the Varanasi Ring Road along the river. Its proposed configuration includes six lane and four lane sections, with much of the route elevated. The works cover the main road, flyovers, loops, ramps and service roads across two packages.
The ministry describes the route as part of the city's decongestion plan, with improved access to Kashi railway station, Varanasi City station, Varanasi Junction, Deen Dayal Upadhyaya Junction and the airport. Ramnagar Port, Sampurnanand Sanskrit University, the ghats and adjoining Chandauli are also among the places named in its connectivity assessment.
What is planned along the Ganga
The Ganga corridor is listed as a 46 km six lane connection between NH 19 and the Varanasi Ring Road. Its proposed works include an elevated main road, a 910 metre cable stayed bridge, a 1.32 km extradosed foot over bridge cum major bridge, loops, ramps, link roads and service roads. It is also divided into two packages.
The release identifies Ramnagar and BHU among the urban destinations that the Ganga alignment is intended to serve. It also names Kashi Vishwanath Temple, Namo Ghat, Ramnagar Fort and the ghats, alongside highway, railway, airport and inland waterway connections. These are the ministry's stated connectivity benefits, rather than a published list of new local entry points.
For the Varuna corridor, the ministry projects a journey between NH 31 and Kashi railway station of about 20 minutes, compared with roughly 40 minutes currently. For the Ganga corridor, it gives an average journey reduction from around 60 minutes to 20 minutes, and a separate NH 19 to Kashi station comparison of about 50 minutes to 25 minutes.
The projects are designed for operating speeds of 80 to 100 km per hour, according to the release. Those design figures and projected journey times concern the proposed corridors. They do not set a new speed limit on existing streets or establish a guaranteed journey time through the present road network.
What residents should watch for next
The ministry expects better connections to help the movement of agricultural produce, industrial goods, construction materials and minerals. For the Varuna project it identifies the Chandauli economic and social nodes and six major logistics nodes. Its assessment links the corridors with wider passenger and freight connections across eastern Uttar Pradesh.
The November 27 information leaves the next contracting steps open. A resident or business following a particular stretch will need a subsequent official announcement for contractor selection, work scheduling or any effect on local access. This release reports the response to the tender packages and does not provide those further decisions.
Separate local coverage explains the airport expansion review, the Ramnagar port rail land gazette and the November 28 traffic arrangements. Those notices concern their own works or travel arrangements; their schedules should not be applied to the two elevated corridor projects.