VARANASI: A construction review at Lal Bahadur Shastri International Airport in Babatpur on Friday, November 20, 2026, put the new terminal building at about 71 per cent completion and the runway underpass project at about 60 per cent. The inspection identified separate completion targets: March 2027 for the underpass and July 2027 for the terminal, providing a new construction update for passengers and residents using the Varanasi to Lucknow corridor.

Divisional Commissioner K. Vijayendra Pandian inspected the terminal construction and the tunnel project beneath the runway, according to corroborated reports published on November 20 and 22. Officials of the executing agencies and Airports Authority of India briefed him on progress. He asked them to meet the stipulated schedules while maintaining construction quality.

Residents using the NH 56 airport corridor should distinguish those construction targets from an opening announcement. The inspection accounts do not establish an operational start date for the new facilities or a fresh road diversion. Passengers should continue to use their airline's current terminal and reporting instructions when planning a journey.

Two construction packages, two target months

The terminal review recorded roughly 71 per cent physical completion, with July 2027 identified as the target for completing the building. The commissioner sought details about the pace of work from the airport authority and the construction agency. The reports describe the terminal's design as incorporating elements of Kashi's cultural heritage alongside passenger facilities.

The separate inspection of the NH 56 runway underpass recorded progress at around 60 per cent. The project is intended to carry road traffic beneath the expanded runway, preserving road connectivity while providing space for the airport's airfield development. March 2027 was the completion target given during the review.

The underpass is reported to be approximately 2.89 kilometres long, with an estimated cost of Rs 649.44 crore. The commissioner instructed National Highways Authority of India officials and the executing agency to speed up work. Coordination between the agencies, regular monitoring and prompt resolution of construction bottlenecks were among the directions reported from the inspection.

  • Inspection date: November 20, 2026.
  • New terminal: about 71 per cent complete, with July 2027 as the target.
  • Runway underpass: about 60 per cent complete, with March 2027 as the target.
  • Road connection involved: NH 56, the Varanasi to Lucknow corridor.
  • Underpass project estimate: Rs 649.44 crore.

What the approved airport expansion contains

The Cabinet's June 19, 2024 approval provides the baseline for understanding the wider airport programme. It approved an estimated Rs 2,869.65 crore for development that included the terminal, apron extension, runway extension, a parallel taxi track and associated works. That is the approved airport development estimate, rather than a new expenditure sanctioned at Friday's inspection.

The approval set a goal of increasing the airport's total annual passenger handling capacity from 3.9 million to 9.9 million, equivalent to 39 lakh and 99 lakh passengers. These figures describe capacity. They do not mean that 99 lakh people are currently passing through the airport each year.

The same approval described a new terminal covering 75,000 square metres, designed for six million passengers annually and 5,000 passengers during a peak hour. The whole airport's 9.9 million capacity and the new building's six million design capacity are different measures in that official document and should be read separately.

The approved airfield works include a runway measuring 4,075 metres by 45 metres and a new apron designed to accommodate 20 aircraft. Environmental measures named in the approval include energy optimisation, waste recycling, solar power, lower carbon emissions and greater use of natural daylight. These are features of the approved plan, not a claim that each has already been commissioned.

What residents should do

For an upcoming flight, check current instructions through the airline and the airport authority's Varanasi page. A construction percentage does not identify a passenger entrance, a check in counter or a changed departure time. Anyone arranging a pickup should use the terminal information attached to that particular flight.

The distinction also matters for people using the highway without entering the airport. The March target refers to finishing the underpass project. It does not, by itself, establish when a particular traffic lane will open. Any journey affected by construction should be planned using current instructions at the site.

Earlier local reports on fog related departure delays and three flight diversions explain separate operational disruptions. Readers arranging accommodation can also consult the tourism policy changes affecting homestays. None of those earlier developments establishes an opening date for the facilities reviewed on November 20.