GURUGRAM: ACME Solar Holdings disclosed on Wednesday, November 18, 2026, that its subsidiary had signed a 150 MW hybrid power purchase agreement with NTPC, with supply scheduled to begin on June 30, 2028. The company, which lists its corporate office in Sector 30 and registered office in Sector 44, set out a tariff of Rs 3.21 per unit and a 25 year project tenure from the scheduled supply date.

The agreement concerns generation outside Gurugram. The accompanying company announcement identifies project locations at Bhadla in Rajasthan, Jambkhabalia in Gujarat and Mandsaur in Madhya Pradesh. It is a corporate development involving a business based in the city, rather than a change to the electricity tariff paid by Gurugram households.

What the NTPC agreement covers

The November 18 exchange disclosure identifies ACME Alpha Renewables Private Limited as the subsidiary that executed the agreement under NTPC's Hybrid IV tranche. Its annexure classifies the contract as domestic and identifies NTPC Limited as the awarding entity. The disclosed capacity is 150 MW, with the commencement date and project tenure stated separately.

In the attached announcement, ACME says the project will combine solar and wind generation with energy storage to serve the buyer's requirements, including peak demand periods. The company says the Central Electricity Regulatory Commission has already adopted the tariff. It also reports securing central transmission connectivity for Jambkhabalia and Mandsaur.

Those are company disclosures about the project and its arrangements. The filing does not announce the start of commercial supply under the new NTPC agreement. Its scheduled commencement remains June 30, 2028. The Rs 3.21 figure is the contract tariff stated for that agreement, and cannot be substituted for a local distribution company's consumer bill rate.

  • Contracted capacity: 150 MW.
  • Buyer: NTPC Limited.
  • Contract tariff: Rs 3.21 per unit.
  • Scheduled supply commencement: June 30, 2028.
  • Project tenure: 25 years from the scheduled commencement date.

Where the contract sits in the portfolio

ACME's announcement places its under construction contracted capacity at 5,380 MW. Of that, it says 5,080 MW is now covered by signed power purchase agreements following the NTPC transaction. The difference between the two disclosed totals is 300 MW. These are figures for the under construction portfolio, rather than a claim that all those projects are already generating electricity.

The company separately describes a total contracted portfolio of 8,370 MW across its renewable generation and storage businesses. It reports operational generation capacity of about 3,190 MW and battery storage capacity of 5.90 GWh in the announcement. The distinction matters because a contracted project, a component that has been commissioned and an operational generating asset describe different stages of delivery.

A separate November 17 commissioning update

A second official filing, dated November 17, reports an additional commissioning at Kelan village in Chhatargarh tehsil of Bikaner district, Rajasthan. That update concerns ACME Greentech Seventh Private Limited, a wholly owned subsidiary, and a different project whose power purchase agreement is with SJVN Limited.

The newly commissioned component is stated as 52.32 MW with 209.28 MWh of discharge capacity. The company scheduled its commercial operation date for November 19, 2026. The update brings cumulative commissioned discharge capacity for that project's storage component to 247.67 MW and 990.68 MWh, against a stated project discharge capacity of 300 MW and 1,200 MWh.

The same filing gives installed storage capacity of 247.67 MW and 1,321 MWh. Its installed energy figure and discharge energy figure are different measures printed in the document. They should not be exchanged or added together. The Kelan commissioning also should not be presented as commissioning of the separate 150 MW NTPC agreement announced the following day.

Earlier operating context

In its October 29 earnings call transcript, management had reported quarterly generation of 1,840 million units, up 19.6% over a year, and capacity utilisation improving from 24.1% to 27.8%. Those historical operating figures provide context for the company's expansion; they are not generation figures for the newly signed contract.

The same historical call reported quarterly revenue of Rs 1,007 crore, an increase of 67.5% over a year, and profit after tax of Rs 269 crore, up 133.5%. Management attributed the revenue performance primarily to short term peak power storage operations and renewable capacity additions. These results relate to the quarter discussed on October 29 and do not represent revenue already earned from the November 18 NTPC agreement.

The current filings give two distinct milestones to track: the November 19 commercial operation date stated for the additional Kelan storage component and the June 2028 supply schedule for the NTPC agreement. Other recent Gurugram corporate disclosures are covered in the reports on GRM's quarterly results, Zuari's income figures and Shalimar's proposed office move.