JCB Hits Underground 11 kV Line in Dalmandi; Ward 69 Faces Daytime Outage

A JCB clearing leftover demolition debris in Dalmandi under Aadi Vishweshwar Ward 69 damaged an underground 11 kV line on Friday morning, cutting electricity across the pocket while power department crews began repairs.
Local accounts and field information place the fault near the Musafirkhana and Purani Adalat crossing around 11 am. The machine was removing debris from ongoing clearance work when it struck the buried 11 kV conductor. Supply to the surrounding lanes dropped at once, leaving shopkeepers and residents without power through the middle of a working day.
Electricity department staff reached the spot after the fault was reported, began locating the damaged section and started repair preparations. Officials indicated that a technical team was expected after about 5 pm to complete the jointing and restoration work, with an evening target to return supply once the underground repair held.
Unplanned cable hits during debris clearance are a familiar monsoon-and-rebuild hazard in the old-city wards, where LT and HT runs sit shallow under patched road crust. Ward 69’s Dalmandi stretch mixes wholesale shops, walk-up residences and narrow turns that leave little room for a JCB boom to miss a buried route when maps are incomplete. The civic point is not to invent blame charts; it is to log the outage, the approximate time, the 11 kV voltage class and the evening restoration push.
Shopkeepers who lost billing machines and weighing scales mid-morning usually switch to phone hotspots and cash till supply returns. Cold storage for dairy and sweets on the same lanes is the softer risk if the cut stretches into the evening. Residents on upper floors should treat lift use as unsafe until the feeder is confirmed live again. Temporary generators on footpath edges can help a few shops; they do not restore street lighting or water pumps fed from the same circuit.
Old-city underground maps are often patchy after years of dig-and-fill for water and telecom. A debris-clearance contractor working on leftover demolition rubble may not see a cable marker that was never reset after the last road patch. That is why power crews treat Friday’s strike as a locate-and-joint job first, and a paperwork question later.
This brief does not claim a citywide blackout or invent injured persons. It is a Ward 69 Dalmandi utility incident: Friday morning, JCB, underground 11 kV, Musafirkhana–old court crossing, power staff on site, evening repair target. If restoration slips past nightfall, a later control-room update would be needed; until then the evening target stands as the department’s working aim.
For readers comparing this with Thursday’s planned Pandeypur feeder shutdown, the difference is obvious. Thursday was a notified two-hour construction cut. Friday’s Dalmandi trip was an accidental cable strike during debris work. Both belong on the electricity desk; only one was on the clock before it happened.
Sources and reporting
Fri 25 Sep ~11 am, Dalmandi, Aadi Vishweshwar Ward 69. JCB clearing demolition debris damaged underground 11 kV near Musafirkhana–Purani Adalat crossing. Area outage; power staff on site; technical repair push after ~5 pm with evening restoration target.
Related Stories

VMC Launches Doorstep E-Waste Pickup With On-the-Spot Payment

Family Alleges Youths Chased Car, Assaulted Women and Children Near V-2 Mall in Lanka

Sigra-Trained Shooter Kamaljeet Wins Asian Games Gold in Mixed Air Pistol

Sarnath Police Arrest Three Over Locked-House Burglaries, Claim ₹7 Lakh Recovery

NER Varanasi Division Runs 2,915 Chlorine Tests on Station and Colony Water