GURUGRAM: Municipal commissioner Dr Pankaj directed engineers on Thursday, November 26, 2026, to obtain site clearance before preparing development estimates and secure the ward councillor's satisfaction certificate after completing work. The review covers municipal projects across Gurugram, including roads, drinking water lines and sewers, and sets fresh checks for agencies carrying out neighbourhood improvements.
The corporation's official directory lists Pankaj's office at Plot C-1, Info City, Sector 34. For residents and welfare associations, the directions connect three stages of a project: checking that the site is available, inspecting construction while it is under way, and confirming that finished work can actually be used. Local reports of the engineering review agree on these requirements.
Clear the site before calculating the cost
Engineers have been told to inspect proposed sites and establish that there is no unresolved dispute or encroachment before preparing an estimate. The site clearance certificate belongs at this preliminary stage. It is intended to prevent a project from reaching construction before officials discover an obstacle on the land where the work is supposed to happen.
Road and street estimates must identify the stretch covered by the proposed work. The review also directed engineers to consider the defect liability period when preparing estimates. These instructions concern the definition and terms of the work, alongside the amount being estimated.
Junior engineers must regularly inspect projects in their wards. Assistant engineers and executive engineers have also been directed to visit sites periodically. Chief engineer Vijay Dhaka and officers from the engineering wing attended the review, which placed responsibility for checking execution across the engineering hierarchy.
The commissioner also asked officers to give priority to works suggested by elected representatives and resident welfare association representatives, and to maintain communication with them. Those suggestions are to inform project selection alongside the assessed needs and facts of the proposed work.
Completion requires a usable project
The review's completion test is whether the development work is fully usable. Once work has finished, the relevant councillor's satisfaction certificate must be obtained. The instruction adds a local representative's confirmation to the process of treating a municipal project as complete.
Agencies that leave work unfinished beyond the stipulated period, or fail to meet quality requirements, are to receive notices within a week. The reported directions provide for penalties, blacklisting or termination of contracts under the applicable rules. The notice instruction is a deadline for action by officials, rather than a statement that a particular contractor has already been penalised.
Sample reports for development works costing more than Rs 50 lakh must go to the commissioner's office. Contractors are also to attend a special workshop explaining quality requirements, prescribed procedures and contract conditions. Together, these instructions address inspection during execution and the standards agencies are expected to follow.
- Before estimates: inspect the site and obtain clearance.
- During execution: regular ward inspections and periodic visits by senior engineers.
- For works above Rs 50 lakh: send sample reports to the commissioner's office.
- At completion: confirm usability and obtain the councillor's satisfaction certificate.
Road survey and ageing utility lines
Pankaj directed the corporation to survey all city roads and complete tendering in time for road improvement work to begin in January and finish by the end of May. These are the targets reported from the November 26 review. They are not a road by road construction schedule or confirmation that the relevant contracts have been awarded.
The engineering wing was also asked to begin work towards replacing drinking water and sewer lines that are 30 years old. Road construction must follow the Commission for Air Quality Management's requirements, including dust and pollution controls.
Other directions covered grills along municipal green belts and road dividers, additional greenery and good quality streetlights. Engineers were asked to prepare proposals for parks, libraries and swimming pools, while reviewing unfinished projects and prioritising their completion.
The official office directory publishes 0124-2370911 for the commissioner's office. It also lists the chief engineer's office at the Sector 34 address. The directory provides institutional contact details; the review reports supply the new engineering directions.
The municipal website also links to its 24 Hours Challenge service and a separate tracker for existing complaints. Residents can use the reporting link for a new issue or the tracking link for an issue already registered. These are separate options on the official site.
Residents can consult the municipal corporation's official website for its services and notices. Related local background includes the earlier Laxman Vihar paving proposal, Sector 41 sewer connection repairs and road cleaning inspection directions.